  1. A. Demolition

    1. Demo existing backyard hardscape - Allowance

    until site survey 950 S.F. $ 3.50 $ 3,325.00

    2.

    Demo existing backyard sod in immediate

    construction area- Includes all sod- back and right

    side slope to be reviewed and bid separately bid-

    Allowance until site survey 690 S.F. $ 2.00 $ 1,380.00

    3. Saw cut and remove concrete for plumbing lines

    at right side yard 55 S.F. $ 3.00 $ 1 65.00

    TOTAL A: $ 4,870.00

    B. Gas & Electrical

    1. Gas run to BBQ-T'd off from heater run 14 L.F. $ 10.00 $ 140.00

    Gas run to optional fire bowl-T'd off from heater

    run 38 L.F. $ 10.00 $ 380.00

    2. Electrical for BBQ 71 L.F. $ 9.00 $ 639.00

    Electrical to loggia- Looped from BBQ run 25 L.F. $ 9.00 $ 225.00

    Electrical 220v for patio cover heater from

    electrical main 105 L.F. $ 10.00 $ 1,050.00

    Electrical for landscape lighting transformers if

    needed 15 L.F. $ 9.00 $ 135.00

    3. GFI Outlets at BBQ 3 EA. $ 145.00 $ 435.00

    GFI Outlet- Misc 2 EA. $ 145.00 $ 290.00

    4. Electrical and Gas Permits $ 350.00

    TOTAL B: $ 2,459.00

    1 of 8

    C. POOL AND SPA

    1. Standard features included in your Dreamscapes pool and spa:

    ■ Pre-construction meeting with project manager to review pool layout prior to dig

    ■ All steel reinforcing to meet or exceed engineering specifications and local building codes

    ■ Steel to have 3" clearance from soil for proper shotcrete thickness and structural integrity

    ■ Non corrosive pool plumbing above ground is U.V. protected to prevent rusting

    ■ Schedule 40 PVC plumbing for entire pool circulation system

    ■ All plumbing to be pressure tested throughout construction

    ■ Filter to have backwash line connection to 3"sewer line to clean out filter & drain pool

    ■ Solid conductor bonding of the steel pool structure

    ■ 4,000 PSI Shotcrete used to resist structural stress factors & increase the

    integrity of the pool shell

    ■ Pool and spa interior to be hand troweled white plaster

    ■ Cleaning tools (Pool brush, leaf net, telescoping pole, and thermometer)

    ■ Pool start up w/ labeled valves and pipes for owner's convenience

    2. Pool size- 28'- 6" x 14' at widest points 368 S.F. $ 31,200.00

    86' perimeter

    Pool depth to be 3'-6" to 5'-6"

    3. Spa-7' x 7' (49 s.f.) w/ 6 therapy jets $ 5,200.00

    28' perimeter; Spa raised 18"

    6 jets total for spa; Depth to be 3'-6"

    Optional extra 4 standard jets for 10 jets total-

    Extra pump required 4 EA. $ 100.00 $ 400.00

    Upgrade 10 standard jets to oscillating massage

    and pulsating jets 10 EA. $ 65.00 $ 650.00

    4. Pool Plumbing with Hayward equipment: $ 5,850.00

    400k B.T.U. H Series heater; Echostar Variable

    Speed pump for circulation; 60 S.F. D.E. filter;

    White LED lights for pool and spa (one each- two

    total)

    Upgrade LED lights to color changing lights 2 each $ 350.00 $ 700.00

    Additional pump for independent control of sheer

    descent water feature 1 each $ 950.00 No Charge

    Additional pump for additional jets, if option is

    taken 1 each $ 1,025.00

    5. Auto re-fill line to pool $ 350.00

    2 of 8

    6. Distance of plumbing from pool and spa

    equipment 80 L.F. $ 20.00 $ 1,600.00

    Plumbing for sheer decent water features 1 EA $ 450.00 $ 450.00

    7. Gas line from meter of house to pool and spa

    equipment trenched 18" under grade 138 L.F. $ 13.00 $ 1,794.00

    8.

    Electrical at pool equipment- Includes: Sub panel,

    junction box, GFI, heater and pump hook up. Base $ 2,000.00

    Electrical main line from meter to pool equipment

    and to pool light 135 L.F. $ 9.00 $ 1,215.00

    9. Automatic Salt Chlorinator system $ 1,250.00

    10. Upgrade white plaster to Stonescape Mini

    Pebble Finish for pool and spa 109 L.F. $ 44.00 $ 4,796.00

    11.

    Hayward ProLogic PS-4- includes Aqua Connect

    for Home network/internet capability; wireless

    antenna, and wireless spa remote puck. No

    indoor keypad given- homeowner can use any

    Ipad or Android device for system control 1 EA $ 2,960.00 $ 2,960.00

    12. Pool Raised Bond Beam:

    Raised +12" 28 L.F. $ 40.00 $ 1,120.00

    Raised +24" 12 L.F. $ 70.00 $ 840.00

    13. 5' PVC Sheer descent water feature 1 EA $ 950.00 $ 950.00

    14.

    Heliocol Pool Solar System- 4o0s.f. system.

    Includes full 10 year warranty on collectors, parts,

    labor and installation- Allowance until site

    survey by solar technician $ 5,485.00

    15. Manual Fire bowl at back wall of pool- Essex 31"-

    Includes lava rock 1 EA $ 1,885.00 $ 1,885.00

    Plumbing requires access to sewer P-trap. If not easily accessible extra

    charges could apply.

    Upgrade of existing electrical panel , if necessary, is not included in this

    proposal and to be paid direct by homeowner to electrician.

    3 of 8

    16.

    Soils testing and engineering will be required for

    new pool per city requirement. Costs to be paid

    direct to Soils Engineer for all testing and

    reports. Approx. costs $800.00

    17. Trash & haul away after shotcrete $ 500.00

    TOTAL C: $ 59,115.00

    D. Back Yard

    1. P.I.P. colored concrete pool and back pool wall

    coping w/ standard straight edge coping 116 L.F. $ 30.00 $ 3,480.00

    2. Travertine waterline tile @ pool and spa (up to $5

    per s.f. allowance) 55 S.F. $ 2 2.00 $ 1 ,210.00

    Add travertine tile veneer to spa spill way (up to

    $5 per s.f. allowance) 4 S.F. $ 2 2.00 $ 8 8.00

    3. Stone panel veneer at 12" and 24" H back pool

    wall and outside of spa face- (stone to have a

    $8.00 per s.f. allowance) 108 S.F. $ 28.00 $ 3,024.00

    4. Travertine paver decking on sand base- (up to

    $5.00 per s.f. allowance) - Add $1.50 per s.f. for

    Versai pattern 866 S.F. $ 15.00 $ 12,990.00

    Olson Concrete paver decking on sand base-

    (pavers up to $3.00 per s.f. allowance) 866 S.F. $ 12.00 $ 10,392.00

    Concrete Band around portion of decking 165 L.F. $ 11.00 $ 1,815.00

    5. Open beam patio cover, 8x8 wood posts, 8x10

    header beams and 6x8 joists, 2x3 shade boards,

    Douglas fir primed and painted, Down lights or

    ceiling fan by separate bid

    238 S.F. $ 8,550.00

    Permits and engineering $ 800.00

    Overhead structure footing- Allowance until final

    engineering, based on 2'x2'x2' dimensions 2 EA $ 350.00 $ 700.00

    4 of 8

    6.

    Solid Overhead Structure 17' x 14' (includes

    Gable roof, beams, 8x8 pressure treated wood

    posts, tile roofing to match house, open beam

    ceiling, etc)- allowance until final engineering

    and detail specs 238 S.F. $ 7 0.00 $ 16,660.00

    Engineering for cover- Allowance $ 1,200.00

    Overhead structure footing 2 EA $ 650.00 $ 1,300.00

    Option price for Low Voltage lights throughout

    cover w/ transformer 4 EA $ 185.00 $ 7 40.00

    Seamless aluminum raingutters- Ogee style w/

    paint 1 EA $ 985.00 $ 9 85.00

    Cable TV conduit run to family room (TV, all

    audio, cable and TV installation by owner)-

    Allowance on l.f. until confirmed run 68 L.F. $ 3.00 $ 204.00

    Hook up of owner provided ceiling fan 1 EA $ 325.00 $ 325.00

    Infratech Heater- W- Series- 60" Dual Element

    w/ install- Needs 220V elec. Run 2 EA $ 1 ,125.00 $ 2,250.00

    Switches for Infratech Heaters 2 EA $ 150.00 $ 300.00

    7. 30" High structure columns 2 EA $ 525.00 $ 1,050.00

    Stone panel veneer at column- (stone to have a

    $8.00 per s.f. allowance) 35 S.F. $ 28.00 $ 980.00

    8.

    36" High BBQ and serving counter structure with

    smooth stucco veneer and travertine tile

    countertop (up to $5 per s.f. allowance) 17.5 L.F. $ 315.00 $ 5 ,512.50

    Add bi-level smooth at 42" H w/ tile veneer

    counter top 12 L.F. $ 45.00 $ 5 40.00

    9. Gravel at pool equipment area 50 S.F. $ 3.00 $ 1 50.00

    10. Site Preparation, light grading, Dump And

    Recycling Fees $ 1 ,200.00

    TOTAL D: $ 52,924.50

    BBQ and access doors supplied by owner and installed by Dreamscapes.

    Additional hardware provided by owner and installed by Dreamscapes at

    $125/piece

    5 of 8

    E. Right Side

    1. Color Concrete to replace saw cut of existing

    concrete for main plumbing lines 55 S.F. $ 8.00 $ 4 40.00

    2. 5' High block retunr wall with stucco cap and

    stucco veneer faces to match exisitng removed for

    dig access 2 L.F. $ 115.00 $ 2 30.00

    New pool safe fencing and gate by owner or

    separate bid

    TOTAL E: $ 670.00

    F. Irrigation- Backyard only

    1.

    Automatic sprinkler valves pop ups & spray

    heads with Rain Bird- allowance until site survey

    and pressure test; Damage of existing irrigation

    is to be expected during construction.

    Dreamscapes will do it's best to limit damage

    and repair of existing irrigation will be by

    separate bid once site review can be done after

    demo and pool dig 3 Each $ 700.00 $ 2,100.00

    Existing Automatic station timer to be used

    Drip irrigation and drainage for pots 2 Each $ 75.00 $ 150.00

    Pot prep and installation of owner provided potsallowance

    2 Each $ 80.00 $ 160.00

    Drainage- Backyard only, to tie into existing line on side yards.

    1. Drainage- 4" SDR 35 pipe with Brass Drain

    Grates- Drains to tie into existing drains at back

    and side yards 275 L.F. $ 8.25 $ 2,268.75

    TOTAL F: $ 2,268.75

    G. Lighting- Price reflects matte bronze finish

    1. Directional lights Top-UL142MBR- LED 10 Each $ 125.00 $ 1,250.00

    Pot light Top-UL-118-MBR LED 2 Each $ 130.00 $ 260.00

    Path lights- Top-PL358-MBR LED 3 Each $ 135.00 $ 405.00

    Wall Washer- Top-WL454-MBR- LED 0 Each $ 130.00 $ -

    Transformer with timer- 300 W 1 Each $ 500.00 $ 500.00

    6 of 8

    Direct burial cable with trenching and connectorsallowance

    dependant upon final lighting runs 100 L.F $ 2 .25 $ 225.00

    3" Sleeves for future access- allowance dependant 50 L.F $ 4.00 $ 200.00

    TOTAL G: $ -

    H. Planting

    ***Crane fees for Olive Trees and 48" trees or larger are not included and to be paid direct by owner

    1. 24" box Tree 2 each $ 375.00 $ 7 50.00

    2. 15 gal shrubs 5 each $ 125.00 $ 625.00

    15 gal premium shrubs 2 each $ 175.00 $ 350.00

    3. 5 gal shrubs 45 each $ 31.00 $ 1,395.00

    5 gal premium shrubs 20 each $ 39.00 $ 780.00

    1 gal shrubs 25 each $ 11.00 $ 275.00

    1 gal premium shrubs 15 each $ 15.00 $ 225.00

    Flats of ground cover 0 each $ 30.00 $ -

    Flats of annual color 0 each $ 30.00 $ -

    Flats of premium annual color 0 each $ 60.00 $ -

    4. Marathon II Sod- Allowance on s.f. 170 s.f. $ 3.00 $ 510.00

    Soil preparation & amendments (Agriform

    tablets, organic fertilizer, compost, & 15-15-15

    starter) 4 Yds $ 125.00 $ 500.00

    Tree staking 0 each $ 30.00 $ -

    Rootbarriers 0 each $ 40.00 $ -

    Bark topper- allowance on yds 6 Yds $ 500.00

    Removal of extra dirt after plant installation-

    Allowance only; Price shown is for one 2 ton

    truckload each 1 EA $ 275.00 $ 500.00

    TOTAL H: $ -

    $ 122,307.25

    Exotic/Specialty plants or trees to be bid separately

    GRAND TOTAL OF ITEMS A -H ====>

    7 of 8

    Special Notes

    * All proposal items above in blue text are options and not currently included in proposal total

    *

    *

    *

    *

    *

    *

    and self closing latch at 54" high by owner

    *

    * Visit www.gardenpassages.com for custom wooden gates

    *

    *

    *

    *

    *

    BID HONORED FOR 60 DAYS

    PAYMENT SCHEDULE

    $ 1,000.00 1 Signing of Contract

    $ 3,892.29 2 Pool Plans, Permits, & Engineering

    $ 4,892.29 3 Commencement of Demo

    $ 14,676.87 4 2 Days before Pool Excavation

    $ 19,569.16 5 Commencement of Plumbing & Steel

    $ 18,346.09 6 Day of Shotcrete

    $ 14,676.87 7 Commencing of drains

    $ 8,561.51 8 Completion of pool coping

    $ 3,669.22 9

    $ 9,784.58 10

    $ 14,676.87 11 Commencement of patio cover

    $ 3,669.22 12

    $ 4,892.29 13

    $ 122,307.25 Grand Total

    All tile to have a $5.00 per s.f. allowance

    All stone paving is non- tumbled unless stated in proposal as tumbled. Tumbled to cost an

    additional $2.00 per s.f. for random stone paving

    Day of Pool Plaster- Must be paid day of or

    All stone and tile allowance to include material cost, tax, shipping and delivery costs

    BBQ equipment, pots, pre-fab waterfeatures, and furniture are all by owner unless noted

    differently in proposal

    All Pots to be provided by owner with proper hole diameter for plumbing. If Dreamscapes has

    to drill the pots owner understands that no warranty can be given on pot and that cracking

    can occur.

    Garage man door to have spring & self closing latch @ 54" high by owner

    Upon delivery of pavers

    50% Completion of block structures

    All soils report if required are by Owner

    Modifications for existing gate to swing away from pool area with spring

    All gates by owner unless noted in proposal.

    Day of Pool equipment set

    Repair of any existing drainage or irrigation damaged due to excavation or construction of

    new pool is not included in this proposal.

    If required, upgrade of existing electrical panel is not included in this proposal.

    Door alarms per city codes at all exterior doors leading to pool area are by owner. Door

    alarms may not have a on/off switch

    8 of 8

×
×