Gunite Pool Not Level - 2.5"


mdjtlj

Recommended Posts

Greetings,

We've got an eight year old gunite pool here in Houston, TX. The pool has the following characteristics:

- 40 ft long

- 24 ft wide

- 6 ft deep end

- 3.5 ft shallow end

- 12 man raised hot tub, situated near the deep end

- approx 40,000 gallons or so

Originally when the pool was built, it was level, however, over the years it has settled, so that the deep end is about 2.5 inches lower than the shallow end. I don't know how to tell if it is the deep end which has sunk or the shallow end which has floated up, I suspect that it is the shallow end which has floated up due to the cracks in the decking (hairline). Also, if you take a transit and shoot the pool, the deep end to about the mid-point is level, from this midpoint to the shallow end is where the rise occurs. This troubles me, as the rise is concentrated in a shorter portion of the pool and is therefore more pronounced and I can only imagine the stresses invoked at the point where the kink is.

It is to the point now that the shallow end skimmer is close to being not covered, especially if the level gets a little low.

Our question is, what can be done about the level of the pool? How is this typically fixed? We've had some people tell us that you will dig out the skimmer on the shallow end and make it deeper, but that just seems kinda wrong and not a true fix for what is going on. What have others done in this case?

I've talked to the original builder who gave us a life-time structural guarantee and he indicates that unless the shell is cracked there is nothing that he's going to do. Even if it does crack, I'm sure we'll have to fight him tooth and nail.

Michael

Link to comment
Share on other sites

First, you'll need a soils report from a soils engineer. If the pool raised or lowered, it means the soil moved. A pitched shell usually means expansive soil (clay usually) as a bed for the pool to rest on but can also be caused by creeping soil.

Scott

Link to comment
Share on other sites

Trying to think if a soils report would tell you anything you don't already know. It moved! Do i want to spend the money to find out exactly how? And the why is irrelevant, it already happened, you can't change that.

Not trying to bag on you Scott, just don't know if a report would be a benefit at this point.

If you were going to demo the pool and start over, definitely, a soils report. Because then, you can do something about it. But who has that kind of money?

If the decks are going to come out for this, you can build up the bond beam on the low side, and re-tile the pool to make it level again. Since the difference is over two inches, you should have the guy use spikes driven into the bond beam to help stabilize the build up. Downsize is that your finish grade elevation around the affected area of the pool is now going to be higher +/- 2.5 inches., but if you plan on new decks, The contractor may be able to make it look not so noticeable.

Having said that. That pool may, and probably will move again.

Link to comment
Share on other sites

How are you going to prevent it from doing it again after it's fixed? That's the purpose of the report, It'll say if drainage is needed and where it is suggested.

Lets say it was just mud jacked level. Two years of normal to heavy rain soak the ground and cause any clay finding the moisture and swell. Two years of dryer than normal conditions and the swollen clay has now shrunk. This time, the deep end sinks. Putting drainage where needed keeps the moisture away. Digging out a new bed and refilling it with something more suitable or mud jacking services aren't cheap. Doing it twice? Nah.

Scott

Link to comment
Share on other sites

Here's the Wiki on mud jacking, aka slab jacking: http://en.wikipedia.org/wiki/Concrete_leveling

A number of holes are core drilled in the floor and slope. Fill one with the desired amount, reseal the core with hydraulic cement. Continue as needed to right the ship, so to speak. Sometimes cheaper than busting out and rebuilding a gunite pool bottom.

Building up a bond beam and replacing the skimmers so they are at the right height may not keep it from happening again.

Scott

Link to comment
Share on other sites

I imagine each plumbing penetration would have to be exposed, and monitored, maybe even cut before the jack starts.

And at some point, the cost of the leveling fluid would come into play if you started to fill a large void, and it kept taking it... and taking it.

Link to comment
Share on other sites

  • 7 years later...
  • 1 year later...

So what was the out come and what did you do.  I'm going through the same thing but mine is 2" along one side from shallow to deep and I know exactly why mine settled because of crappy drainage and LOTS of standing water, pool was fine and we had HEAVY RAIN AFTER HEAVY RAIN for about 3 months and this is when it settled and hasn't moved since and added drainage very soon after this happen, concrete patio and gutters (no more standing water-proper runoff) I'm thinking of one of two things. Adding to the coping beam, raising that side and what I'd prefer but worried about cold joint or cutting the high side down. 

Link to comment
Share on other sites

Join the conversation

You can post now and register later. If you have an account, sign in now to post with your account.
Note: Your post will require moderator approval before it will be visible.

Guest
Unfortunately, your content contains terms that we do not allow. Please edit your content to remove the highlighted words below.
Reply to this topic...

×   Pasted as rich text.   Paste as plain text instead

  Only 75 emoji are allowed.

×   Your link has been automatically embedded.   Display as a link instead

×   Your previous content has been restored.   Clear editor

×   You cannot paste images directly. Upload or insert images from URL.

Loading...
×
×
  • Create New...